Spring 2020
- Implement Plan
Fall 2019
- Finalize Plan
- Present Plan to Board of Trustees for approval
- Present Final Plan to Committee on University Effectiveness (CUE)
- Present Final Plan to the University community (CUE)
- Develop Implementation Teams
Spring 2019
- Present draft plan to CUE
- Present draft plan to University community
Winter 2019
- Plan drafting continues with goal to present to CUE in Spring 2019
Fall 2018
- Design Teams continue to work based on feedback from CUE Summit II
- Drafting of plan begins with Leadership Team
Summer 2018
- Design Teams work continued in preparation for the August 2018 CUE Summit II
- Design Teams presented preliminary proposals to CUE at the CUE Summit II
March – May 2018
- Engage the University Community around the strategy through participation in Design Teams
March 19-20, 2018
- Future Summit for Committee on University Effectiveness(CUE) to craft core strategy with the President
Winter/Spring 2018
- Stakeholder sampling and engagement in SWOT activities
- Environmental scan by Office of Institutional Research
- Analyze the data collected
Fall 2017
- Leadership Team and Steering Committee engagement in strategic thinking and
planning the process - Strengths, Weaknesses, Opportunities, Threats (SWOT) facilitator planning and
preparation